Full bathroom renovation with modern fittings
LOCATION:
HA4
DETAILS:
DEMOLITION & PREP:
- Complete strip-out of bath, basin, WC, wall tiles, and flooring
- Reuse of existing mirror and towel rail
- Protective setup and waste cleared via on-site skip
PLUMBING:
- WC relocated 500mm to optimise layout
- Concealed dual-outlet shower system installed
- Shower pump added for improved water pressure
ELECTRICALS:
- New ceiling pull switch and shaver socket fitted
- Wiring upgraded to meet Part P compliance
TILING:
- Full-height wall tiling and tiled floor throughout
- Shower zone fully waterproofed and finished with trim detailing
INSTALLATION:
- Slimline tray and dual shower (rainfall + handheld)
- Wall-hung vanity, WC in new location
- Towel rail and mirror reinstalled in updated layout